This is a short progress update as at summer 2022:
We finally obtained planning permission for all the necessary works last December, and were hoping to go on and get building regulation approval quickly so we could continue with the refurbishment.
Since then, some further work has been carried out, but discussions with the structural engineer have taken longer than expected, delaying Building Control approval. However, most of these matters are now resolved, and we are in a position to progress the ground floor interior works - mainly ceilings, partitions, fire alarm systems, etc. We are also hoping that we can attract sufficient funds from smaller grant-givers to carry out some required work on the front elevation, possibly before we reopen.
Refurbishment of the TAAG upper floors will require substantial grant assistance and we are monitoring grant-funding opportunities and pursuing applications as the opportunities arise. This work is likely to take longer than we anticipated pre-COVID and will probably have to be completed piecemeal.